| Week 0 |
Proposal/project acceptance |
 |
| Week 1 |
Initial meeting to develop survey instrument |
| Week 2 |
Initial draft of survey to United Way |
| Week 3 |
Comments/revisions for initial survey by United Way
Revised draft of survey to United Way |
| Week 4 |
Survey approved for execution by United Way |
| Week 5 |
Survey at printer for printing and assembly
Survey is mailed to donors |
| Week 7 |
Cut-off date for receiving completed donor surveys |
| Week 8-11 |
Survey analysis and report development |
| Week 12 |
Complete report delivered to United Way |
A detailed schedule with specific dates for each phase of the project is established once the project is accepted. Projects are scheduled on a first-come, first-serve basis so the amount of time required to complete a project is subject to the availability of Perspectives Consulting Group, Inc. Perspectives Consulting Group, Inc. schedules projects three to six months in advance.
|