Week 1 Project acceptance
Meeting to discuss content of survey
First draft of the survey to district
Week 2 District comments on first draft to Perspectives Consulting Group, Inc.
Week 3 Revised draft of survey to district
Week 4 Surveys approved by district
Week 5-8 Conduct research
Complete phone interviewing and/or collect mail survey data
Week 9-11 Survey analysis and report development
Week 12 Complete report delivered to district

A detailed schedule with specific dates for each phase of the project is established once the project is accepted. Projects are scheduled on a first-come, first-serve basis so the amount of time required to complete a project is subject to the availability of Perspectives Consulting Group, Inc. resources. Perspectives Consulting Group, Inc. schedules projects three to six months in advance.